TX I-30 Widening Project | Update

roadworkd2-png-2

We have the latest update for the Four Lane to Six Lane Texas Interstate 30 project. Here’s what to expect this week:

TxDOT Press Release:
Phase A construction continues…

Beginning the week of September 20:

Expected traffic impacts:

Right-lane closures expected nightly, 8 p.m. to 6 a.m.
Westbound, beginning at Stateline Avenue, moving to the west
Right-lane closures and entrance/exit ramp closures expected nightly, 8 p.m. to 6 a.m.
Eastbound, beginning at FM 989/Kings Highway, moving to the east
Daytime shoulder closures

Planned work:

Extending sections of existing metal beam guard fence (westbound)
Back-filling pavement edges (eastbound & westbound)
Adjusting existing signs (eastbound & westbound)
Removing existing pavement markings and placing temporary markings to prepare for traffic shift to should and outside lane

The following is a link to TxDOT’s general I-30 Corridor Public Information page:

The following is a link to the I-30 Widening Project (the project currently under construction) Public Information page:


Tags: ,